New Connection Dashboard

For cases received during 01/11/2020 to 31/12/2021

Time Limit prescribed as per the Public Service Guarantee Act or Equivalent Act (days)
#
Total Number of Applications received
*
Total Number of applications processed
* *

Average time taken to grant approval (days) Median time taken to grant approval (days) Comments / Notes,
if any
Providing electricity connection upto load of 150 kVA 7

114032

DOM COM IND
96478 16136 1418

111747 (Total Count)

DOM COM IND
94718 15651 1378
1.52 1

# STATE BUSINESS REFORM ACTION PLAN 2020

* Applicants paid their MASD bills and complied all the requisite formalities

** Meters have been installed

For cases received during 01/01/2022 to 20/09/2022

Time Limit prescribed as per the Public Service Guarantee Act or Equivalent Act (days)
#
Total Number of Applications received
*
Total Number of applications processed
* *

Average time taken to grant approval (days) Median time taken to grant approval (days) Comments / Notes,
if any
Providing electricity connection upto load of 150 kVA 7

81330

DOM COM IND
69112 11374 845

78232 (Total Count)

DOM COM IND
66742 10694 796
1.11 1

# STATE BUSINESS REFORM ACTION PLAN 2020

* Applicants paid their MASD bills and complied all the requisite formalities

** Meters have been installed